An offshore platform named Seafox 7 stands in the water, surrounded by calm sea and under a blue sky.
Arkona offshore wind farm | RWE

One of the largest wind farms in the Baltic Sea off Rügen has the capacity to supply up to 400,000 households with renewable energy

Arkona offshore wind farm

The Arkona wind farm is located 35 kilometers northeast of the island of Rügen. The wind farm has a capacity of 385 megawatts and can supply approximately 400,000 households with renewable energy. The investment volume amounts to €1.2 billion. Compared to conventionally generated electricity, Arkona saves up to 1.2 million tons of CO2 annually. 60 turbines of the six-megawatt class from Siemens were installed. Arkona is a joint venture.

The partner companies were able to connect the Arkona offshore wind farm to the grid on time and at lower costs than originally calculated. It took only one year from the first ramming to the first electricity feed-in. Rarely before has an offshore project been completed so quickly. The reasons for the success of the fast completion are the detailed planning and the professionally implemented construction process. This is accompanied by the close cooperation with 50Hertz and the precisely coordinated partial feed-in option into the German extra-high voltage grid, which was made possible by the transmission grid operator before the connection was completed.

Arkona is a joint project between RWE, Equinor and Energy Infrastructure Partners. RWE operates the offshore wind farm on behalf of the partners.

Status: In Operation

Facts & figures

00 kilometers

northeast of the island of Rügen

00

Wind turbines

00 m

height of wind turbines

Electricity for 00

households annually

00 MW

Installed capacity

00

Commissioning

Cooperation & new standards

After initially only the first of 60 turbines went online, further wind turbines were put into operation step by step. The transformer station and all 60 foundation foundations including connecting pieces were installed ahead of schedule. The internal parking cabling for connecting the turbines to the substation was also installed  before planned. Then towers, turbines and rotors were installed on the high seas. In August, together with the first power supply, the Arkona electric offshore substation was also put under voltage. RWE, Equinor and the transmission grid operator 50Hertz share the platform. The optimal timing and technical coordination of the companies is helping to optimise offshore grid connection costs and speed up the energy turnaround.

Setting the pace was already achieved during construction: all 60 steel foundations of the wind farm were sprayed with a special anti-corrosion coating. During the 25-year operating period of the wind farm, several hundred tons less aluminum and other environmentally harmful substances are released.

An offshore wind farm featuring a large substation and several wind turbines in the background amidst calm water.
A view of the yellow structure of an offshore installation, with wind turbines in the background over the water.

Location videos


Impressions of the location

The building's exterior features the logos of Arkona, RWE, and Equinor. Stacked pipes and a crane are visible in the background.
Two individuals in the control room of an offshore wind farm, surrounded by monitors and technical equipment.
Photo: Energy Infrastructure Partners
Offshore wind turbines with a boat in the foreground on open water under a cloudy sky.
Copyright: Paul Langrock
A large offshore wind turbine installation vessel with multiple turbines and a drilling platform in the background.
An aerial view of a large offshore vessel with wind turbine blades and a crane on deck, surrounded by deep blue water.
A row of wind turbine blades with red and white stripes, resting on a concrete surface near the coast.

You might also be interested in

Nordsee One offshore wind farm

The wind farm produces enough green electricity to supply 400,000 households.

To the operating site

Offshore wind farm Kaskasi

Technological research in RWE's sixth wind farm off the German coast

To the offshore wind farm

Nordsee Ost offshore wind farm

Nordsee Ost is one of the largest commercial wind power projects off the German coast.

To the operating site

RWE Renewables Europe & Australia GmbH

RWE Platz 4
45141 Essen
Germany